Thursday, September 22, 2011

Is Friday the day????


The paving crews had to take a rain-day today as you may have seen, but plan on continuing on tomorrow if the weather permits.  The plan for Friday is to finish the last corner of the Brassfield roundabout, the east-bound lane between Brassfield and Boulevard, and the side streets between Henderson and Boulevard, excluding Laura St.  If you have avoided Yelm Hwy in the recent past, here's a couple pictures to prove it.
 
WHEEEEEEE!


That MIGHT be the inspector sending in a status tweet...

Condition "GREEN"

Next week the sound wall, landscaping, and curb/sidewalk crews will be back on site (not much room with the paving happening) and will continue with their work in various places.  Hopefully this work will allow for free flowing traffic.  Starting October 3rd, however, the remaining storm lines will be construction near the east end of the project and could cause some additional delays.  (Hopefully not though!)