Wednesday, December 7, 2011

Dec 7th, 2011


Crews will be out patching asphalt Thursday and Friday this week, Boulevard to Rich Rd, and will be paving on Blvd. Ext., Glemore Drive, and Laura Street.  Please expect delays while the crews are paving and for a while after until it is cool enough to drive on.
 
Curb and gutter has been placed for the remainder of the project, minus a short section near Rich Rd due to some conflicts with utilities.  Crews are busy pouring concrete sidewalk today and for the rest of the week.