Thursday, January 26, 2012

Back to Work 1/26/2012


One crew is out today and Friday reconstructing Boulevard Extension.  50th Court SE and the old Blvd Ext. road had been cut up and patched a few times before this project, so to ensure a good product and proper matching the asphalt was cut further back than originally planned.  When weather permits the area will be re-paved.
Crews will also be out installing light poles on the East end of the project, so make sure to drive carefully until the light comes on in those areas.
The good news came with the bad weather! The snow, rain and debris blown wind put the Yelm Highway drainage system to the test....and it passed with flying colors!