Holiday Schedule:
Monday January 16th:  The contractor is planning on working Monday unless weather does not permit.
 
This week a few more street lights should have been visible at night as the electricians flip the switches on their work.  As more and more sidewalks and ramps have been installed there has be an increasing amount of pedestrians utilizing the new Yelm Highway, so please be wary of crossing pedestrians whether or not the crossing systems and lighting are fully functional. 
 
The west half of the project is coming to a near finish!  Just a few areas of cleanup and a layer of bark around the plants to go!
 
This Friday January 13th the contractor plans on paving a few driveways, weather permitting of course, which most often requires a lane closure.