Thursday, March 4, 2010

March 1-5 Weekly Progress

PSE/Potelco has finished placing the new poles and associated underground conduit from Henderson Blvd east to Laura Street.  They are now dropping back to transfer existing power lines from the old poles to the new poles.  Potelco continues to close traffic lanes as needed with two flaggers, advance warning signs and message reader boards.  At times when working in or very near an intersection, they will be turning off the signal lights and directing  traffic with flaggers for a short period of time.




photo courtesy of  K.Whyte TC Project Inspector