Friday, April 30, 2010
Weekly Update -- April 26th -30th
PSE/Potelco completed their utility relocation and restoration work this week. Sefenco, the sub contractor for Comcast is on site working to relocate their aerial and underground cable facilities. Qwest ( phone), and Pilchuck (natural gas), are close to having their utility permits issued and should be starting their utility relocating efforts in May and June. The general contractor for the project should be officially awarded in late May and we expect them to be on site working in early June depending on their schedule.
Photo courtesy of K. Whyte, TC Project Inspector