Today the contractor has been filling and testing the new waterline at Orvas and Clair-Mar. As the main sanitary sewer lines and main water lines are constructed they will be tied into existing systems on side streets, which will involve tearing up the side street road surface. Currently Brassfield is undergoing this process.
At this point in the process there are three separate crews working on water, storm sewer, and sanitary sewer for the Yelm Highway Project. As mentioned previously you will see separate work on Yelm Highway, at Boulevard heading west, being done by Pilchuck through Puget Sound Energy, installing a new gas line.