Wednesday, October 13, 2010

Update for October 13th, 2010

The contractor will be putting two pipe crews to work, one will be working on the water system, one on storm drainage for the next week.  Water work will be focused on Orvas Court, Village Drive, Brassfield, and Clar Mar and services along the entire route from Clar Mar to Orvas Court.  Storm drainage will be off the road this week (through a private property easement).


Pilchuck will continue work in the intersection of Boulevard Road and Yelm Highway, causing traffic delays.  


Please remember, all businesses are open.


Please be courteous and allow traffic to enter from side roads and driveways.   


Oversize loads are prohibited through the work zone until after the first of the year.