Wednesday, April 6, 2011

Update for April 4th-10th

The Contractor is still scheduled to work on the side sewers (sewer connections that run from the center of the road to the sides of the road), currently just west of Boulevard, moving east until approximately April 12th.
Sanitary Sewer is also currently scheduled to be in the Boulevard intersection  Wednesday April 5th, hopefully out of the intersection by the 12th of April, working east towards Boulevard Extension.
 
If the weather holds fair, a lighting pole is scheduled to be relocated at the Henderson intersection, this coming Thursday and Friday. (Guess that they wouldn't want to do this if a thunderstorm was forecast!)