Update for the week of May 31st, 2011

Remember:  The contractor will be working this Friday June 3rd!  

Construction will return to the Monday through Thursday schedule next week.
 
Curb and Gutter
 
Curb and gutter will continue to be poured on the south side of Yelm Highway between Henderson Blvd. and Brassfield Drive.
 
Mainline Sewer
 
The contractor is steadily making their way east, currently between Stratford Lane and Siskiyou St.  This work is expected to take at least 4 more weeks to complete.
 
Boulevard Roundabout
 
The contractor may begin the creation of the Boulevard roundabout this coming June 6th.  A temporary roundabout will be constructed utilizing cones and signs, and is expected to be completed in one day, followed by the demolition of the signals the next day.  Drivers can expect significant traffic disruptions as this work is done.