This Week
The usual sewer connections between Boulevard and Rich Rd, sound/retaining
wall installation, installation of irrigation, and preparation of
Boulevard-Yelm Hwy intersection, and paving on Friday, possibly
Saturday, and paving Monday. Please expect significant delays at the
Boulevard intersection throughout this process.
By the end of the week both the Boulevard and Brassfield roundabouts should
be able to be used as a roundabout.
Please check out the Washington Department of Transportation website if you
have any questions concerning roundabouts
Boulevard Intersection Schedule
Today (August 9th): Preparation for
Paving Boulevard.
Wednesday August 10th:
Demolishing Traffic Signal/Conversion to roundabout using cones and signs.
Preparation for Paving Boulevard
Thursday August 11th:
Preparation for Paving Boulevard
Friday August 12th:
Preparation for Paving Boulevard. Contractor will be paving the
intersection.
Saturday August 13th:
If necessary the contractor will be paving on Saturday as well.
Monday August 15th:
Paving should be expected on Monday as well.