PSE/Potelco continues to place new poles and pull new power lines from Laura Street east toward Rich Road. They worked through the night on Monday, March 15 to switch over the newly installed power grid to the existing sub station located across from Boulevard Extension Road. Potelco performed this switch-over during the night to minimize inconvenience to local homeowners. Comcast will be starting its utility relocation work on Monday, March 22.
The project is now out to bid with the bid opening set for April 14.