PSE/Potelco continues to place new poles and pull new power lines near the area of the sub station at Boulevard Extension road. Potelco is continuing to work 10 hour days Monday thru Thursday with no work on Fridays. They plan to be done with their relocation efforts on April 22nd. Comcast and Qwest have been issued their utility permits. Comcast plans to start on March 29th, Qwest will be starting after they are complete. The project is currently out to bid and posted on the builders exchange for perspective bidders.
Thurston County Public Works wants to remind you to plan now for alternative routes during the construction. Access to all local businesses will remain open, so please continue to patronize and support them. There could, however, be significant travel delays.
For more project information, visit our website, or call us at 360-754-4580 and ask to speak to the project coordinator.