Friday, January 28, 2011

This Week in Yelm Highway History



LAKEVIEW CONSTRUCTION SET THE WET WELL IN THE SEWER PUMP STATION USING A CRANE ALONG YELM HWY 300’ EAST OF BRASSFIELD DR SE (SEE PICTURES BELOW). THEY WILL RETURN WITH THE CRANE MONDAY JANUARY 31st TO SET THE DRY WELL.



Remember this picture from last week?










Look at how BIG this thing is!!!












THIS WEEK
THE CONTRACTOR CONTINUES TO MAKE SEWER, STORMWATER, ILLUMINATION AND IRRIGATION CROSSINGS OF YELM HWY FROM HENDERSON TO BOULEVARD RD SE.

NEXT WEEK
CONTRACTOR WILL CONTINUE WITH THE STORMWATER, ILLUMINATION AND IRRIGATION CROSSINGS FROM HENDERSON TO BOULEVARD RD SE. THE DRY WELL WILL BE SET WITH A CRAIN APPROXIMATELY 300’ EAST OF BRASSFIELD DR SE. THEY WILL ALSO BE PLACING ROCK TO GET UP TO GRADE FOR THE CURB AND GUTTER FROM HENDERSON BLVD TO JULI CT!




Two Week Look-Ahead on Construction (Work is estimated and subject to change)
Here is a portion of the estimate construction upcoming on Yelm Hwy.
Friday Jan. 28th:  Work halfway between Brassfield and Clar Mar on South Side of Road
Monday Jan. 31th - Wednesday Feb. 2:  Work stretching from Clar Mar to Juli Ct. in center of road
Thursday Feb 3 to Thursday Feb 8th:  Work stretching from  Juli Ct heading East towards Laura St. in the center of the road.