Wednesday, February 9, 2011

Week of February 6th-12th

This Saturday, February 12th, the contractor will be working on a water shut-down and connection at Boulevard Rd SE from Yelm Hwy to 45th Ave SE.  This work will occur from 7:30 am to 3pm.  The Northbound lane will be closed, flaggers will be present alternating one-way traffic through the Southbound lane.

INTERESTING WORK THIS WEEK
The contractor is backfilling the excavation for the sewer lift station .  As they backfill, they remove the shoring plates that held back the surrounding soil from entering the hole.




THIS WEEK
The contractor continues to make sewer, storm water, illumination, and irrigation crossings on Yelm Highway from Henderson to Boulevard Rd SE.  The contractor is also excavating/grading Yelm Highway’s westbound lane for the new roadway from Henderson to Brassfield. 
The roundabout at Brassfield is beginning to take shape as initial grading work begins.
 

COMING NEXT WEEK
The contractor will continue to make sewer, storm water, illumination, and irrigation crossings on Yelm Highway from Henderson to Boulevard Rd SE.  A flow meter vault will be installed above the lift station.  The contractor will also be excavating/grading Yelm Highway eastbound lane for the new roadway from Henderson to Brassfield.