Yelm Highway Update Feb 14th-18th


FYI This coming Monday, February 21st (President's Day), the contractor will be working.

THIS WEEK
The contractor continues to make sewer, storm water, illumination and irrigation crossings on Yelm Hwy from Henderson to Boulevard Rd SE.  The Contractor continues grading Yelm Hwy’s East Bound lane for the new roadway from Henderson to Brassfield.  Grading of the roundabout at Brassfield is progressing.  The contractor will set the flow meter vault above the sewer lift station and install components inside the vault. 

  
NEXT WEEK
The contractor continues to make sewer and illumination crossings on Yelm Highway from Henderson to Boulevard Rd SE.  Waterline work will be taking place on Blvd ext.  Electrical work will take place on/in the lift station.  The contractor will also be excavating/grading for the sidewalk from Henderson to Brassfield.  





INTERESTING WORK THIS WEEK


The contractor is done backfilling the sewer lift station and they have connected it to the force main . (Pictures below)



This is what they put in the big hole from a few weeks back,


















  
AND
The Brassfield Drive roundabout is coming along nicely!