Wednesday, March 2, 2011

Week of Feb 28th - March 5th

The contractor is continuing with sewer installation from Clar Mar towards Boulevard Road. 
The water crew is at Boulevard Extension and traffic will be routed down the new Boulevard Extension alignment for a few days while the water work is being done.  The new Boulevard Extensions is gravel.
 
The sewer pump station is moving forward.  All structures (manholes, vaults, etc.) have been installed and now the internal piping and electrical work is beginning.  Still looking at May for that work to be complete.
 
The electrical subcontractor, Amaya, has been installing wire and foundations for the illumination system starting at Henderson Boulevard and moving east.  They will finish the section from Henderson to about Clar Mar, and then come back later once the contractor is ready for them again.
 
Curb and gutter will be placed using a machine that places the concrete in the correct shape using a form in the shape of the curb and gutter, and follows a string line that is put up at an offset.  The string line is in place from Henderson to Brassfield, and as soon as weather allows, the curb and gutter from Henderson to about Clar Mar will be placed.