Note... ClarMar Lane closure has been delayed. We will repost the new date when scheduled.

A little temporary patching, an average daily traffic of 18,000 cars, even more rain, and what do you get?  Potholes, potholes and more potholes, but nothing the paving machine can't improve.  Crews patched a portion near Boulevard, and as weather permits they will move West towards Henderson patch those potholes.



The crew continues to excavate for the retaining wall and sidewalk.
What lies below? Dan and Rich from Lakeview Construction were more than happy to give us a peak at the Wet Well and its workings inside.  Not much to look at, but it sure gives a good idea how much waste goes through the 22ft x 12ft well, and just a glimpse into the immense amount of excellent work buried below.  Hopefully next week the pumps will be available for a look.  




































Dan from Lakeview Construction is more than enthusiastic about his trade and giving a thumbs up!  This shot gives a bit more perspective to the size of the structure.