HOLIDAY SCHEDULE: NO WORK MONDAY JULY 4th. Contractor will work Tuesday - Friday of the holiday week (July 5th - 8th)
Sanitary Sewer - The End is Nearer!
How near the end? The blue and green bubbles in the image near Stratford Lane and Boulevard Extension are the homeowners sewer connections. There may be a few of those yet, but as for the main line, the last sanitary sewer manhole (#29) is expected to be set in the ground around the 12th of July. After #29 is installed the sewer moves over to the south side of the road and makes a connection into an existing sewer system.
Sidewalks, Curb, Driveways. - Henderson to Boulevard
Most of the concrete work has been completed between Henderson and Boulevard Road, except for a couple sections that require a lot of hand work, or those which have constant vehicle access which prevents entire sections from being poured.
Boulevard Roundabout - No longer on hold!
Due to a couple of utilities that were shallower than expected this work has been on hold for a good month. Now that these conflicts have been resolved, in the next couple weeks they will be fixed and the roundabout construction will commence. Keep a look out about two weeks from now for significant changes in that intersection!
Pulverize, Prep and Pave - Henderson to Boulevard
Starting the 5th of July, beginning from Henderson and heading towards Boulevard, the asphalt will be pulverized, the roadway will be prepared for paving by placing crushed rock down, and then paved. The preparation work is expected to be finished by July 8th, and paving beginning on July 18th.
A note about our Twitter feed: We make every effort to have our daily condition tweet out between 6:45AM and 7:15AM, on the days when the contractor is working in traffic. However, due to our agency process for posting to Twitter, if the field inspector has not gotten information from the contractor by 7:15, the tweet could be delayed while those able to post to Twitter are driving in to the office.