note: The contractor will be working Saturday July 9th.
The contractor is pulverizing (grinding) the roadway from Henderson to Brassfield Dr today. They will continue this work through the 8th of July when they reach Boulevard Rd. The mainline sewer work is nearing Rich Rd and its completion. There will be a crew working on the Remote Chemical Feed Station near Indian Summer as well. The subcontractor continues to install the sound wall near Brassfield Dr SE.