Thursday, July 21, 2011

This Week In Review (and Next Week's Plan)


This Week in Review
Sanitary Sewer
The contractor has run some more sewer lines to individual properties between Boulevard and Rich Rd, as well as finalizing the sanitary sewer manholes between Henderson and Brassfield by applying a coat of light blue epoxy (by Molecular Inc.) to their inside surface.  This was necessary to prevent the concrete from being dissolved due to the natural production of acetic acid  by the organisms which break down the solid waste, but also makes the insides more visible for maintenance.  My does it look pretty!.....until its used that is.
As for the pump station itself, it's ready to be turned on and "all systems are go" as the saying goes.  It's just waiting for the coatings to dry and the final list to be checked off.
Sound/Retaining Wall
So far, most of the walls constructed have been for sound reduction in the surrounding neighborhoods, so here's a photo of one of the retaining walls in action across from Brassfield!
Boulevard Roundabout
You keep hearing about this over and over, (kind of like the Yelm Hwy project) but when is it going to take place?  With those pesky utility conflicts fixed the contractor has just today moved on to installing some remaining stormwater structures at the intersection which they previously couldn't.  When you ask?  Well, in reality the contractor is picking up where it left off, so it looks like a tentative date of August 9th.
Next Week
Most of the major work will be between Boulevard and Rich Rd installing storm water structures, but as always, crews will be installing sidewalk, curb,  and Sound/Retaining walls between Henderson and Boulevard.
There also may be a bit of working going on at the Rich Rd. intersection trying to chase down an old and buried stormwater system and figure out where it goes; no sense in plugging up a perfectly good drainage system!


As an added bonus, here are two photos from last week's paving: